CHICAGO
- The B Terminal at Washington, DC's Dulles airport suffered a catastrophic
breakdown of
their cooling system the summer of 1998, causing the B Terminal to
lose climate control during the hottest days of summer. In response
to this emergency need, NuTemp provided a rental cooling system to
allow normal operation.
Facility engineer, Bill Rushing, called NuTemp on Thursday, July 9th
to discuss options if their chiller plant problems could not be solved
quickly. As events unfolded, it became clear that the chiller plant
would not be repaired quickly, and that a rental system would be necessary.
NuTemp was notified on July 10th that a 2000-ton system would be required
on site, installed, and operational by July 15th. Several options
were available ranging from two to nine chillers, generator packages,
and accessories. It was decided to go with an air-cooled system consisting
of nine chillers, two generators, and two truck loads of accessories.
NuTemp drew upon its nationwide depot network and relationships with
accessory suppliers, to coordinate shipments from five states to meet
the project requirements. NuTemp
rallied its resources to provide the equipment from depots in Florida,
Louisiana, Texas, Illinois, and as far west as California. A design
engineering team produced the initial concept drawings and pieced
together available equipment during a traditionally low point in
seasonal inventory. Next the production and freight teams acted
to coordinate shipments of both chillers and accessories. An installation
team was assembled Friday afternoon, and flown to Dulles Airport
to unload trucks, attach all piping and electrical cabling, and
startup the temporary chiller plant.
The result of teamwork, both within NuTemp and with the customer
and outside suppliers, was extraordinary. Equipment delivered without
incident. Installation work went as planned. Startup occurred well
before the June 15th deadline, providing much needed cooling to
the terminal facility.
The
system consisted of nine chillers (with 18 refrigeration circuits
and 22 compressors), six water pumps, two megawatts of generator
power, specially fabricated headers, and nearly one-half mile of
electrical cable and temporary hoses.
The
option available from NuTemp provided the airport authority with
a high level of reliability, tremendous redundancy, and low risk
in terms of further failure. |