In
order to avoid dramatic shortages in chlorine production, PPG
called on NuTemp to design and build a complex temporary condensing
unit. NuTemp’s staff of application engineers went to work
designing, selecting, and fabricating the components of the specialized,
1000HP condensing unit. The process to design and fabricate the
condensing unit took 4 months. While the machine construction proceeded,
field workers prepared the site for quick installation. It took
two weeks to install and start up the temporary condensing unit.
Since PPG preferred to use its existing evaporator, NuTemp installed
the temporary condensing unit in parallel with PPG’s existing
condensing unit. Both condensing units ran simultaneously for a
week. Afterwards, NuTemp/Longville’s condensing unit was
brought on line before shutting down the permanent PPG condensing
unit. Full capacity was shifted to NuTemp’s temporary condensing
unit.
Central to the plan
was the reliability of NuTemp’s temporary
condenser. The temporary condenser was required to operate independently,
although it was completely intertwined with the permanent system.
Specific functions of the permanent equipment and certain site
requirements meant that a very special design had to be implemented
in order for the two systems to work together. The equipment
ran on 2300V site power, used cold river water (during winter operations,
for condenser cooling), functioned 24/7, and held loads between
0 and 100%. Throughout the project, NuTemp engineers worked closely
with the on-site engineers to ensure that the rental system would
provide the necessary support the permanent and temporary machinery
needed.
There were several unique
factors that made this a challenging project for NuTemp. The
first consideration was that the two
condensing units (the NuTemp rental and the permanent unit) ran
simultaneously
using the same evaporator. Another factor to keep in mind was
that the rental condensing unit had to operate from a remote location,
while managing system oil and refrigerant. The microprocessor
control
located on the temporary condensing unit’s skid kept the
process running smoothly and reliably.
The project successfully completed in April of 2003. The temporary
condensing unit functioned for two months while PPG converted its
permanent condensing unit equipment. The production of chlorine
was kept at normal levels.
NuTemp/Longville’s
ability to undertake complex refrigeration projects on a fast
track basis sets the Company apart from all
other HVACR equipment rental firms. NuTemp/Longville offers industrial
clients quick, expert rental or sale solutions to complex refrigeration
applications.
NuTemp/Longville is
a worldwide leader of specialist utility rental equipment with
11 offices nationwide, and over 50 international
locations. NuTemp serves a wide cross section of markets including
manufacturing, industrial, commercial, governmental, and institutional.
The Company’s rental products include chillers, cooling
towers, air conditioners, spot coolers, air handlers, dehumidifiers,
heaters,
generators and diesel driven pumps. Further information can be
obtained at www.nutemp.com.